Wechat&WhatsApp: +86 13814834140 E-mail: turbomax@126.com

← All maintenance cases

IHI TRA350KW Compressor — Major Overhaul After 38,064 Hours

Second major overhaul of an IHI TRA350KW three-stage centrifugal air compressor at a manufacturing plant: intercooler and diffuser restoration, a new 1st-stage impeller, new low-speed bearings, all air & oil seals and a new discharge check valve.

IHI TRA350KW new first-stage impeller, centrifugal compressor spare part supplied for the overhaul

Machine background

This IHI TRA350KW three-stage centrifugal air compressor was delivered in December 2008 and supplied plant air around the clock. By the time it came in for its second major overhaul the counter showed 38,064 running hours and 3,663 starts; the first intermediate overhaul had been carried out in 2012. The unit had started surging at its normal working pressure — a classic sign that efficiency had dropped because of internal fouling and eroded flow-path parts — so a full overhaul was scheduled.

ModelIHI TRA350KW (three-stage centrifugal air compressor)
Discharge pressure0.9 MPa
Compression stages / gas3 stages / air
MotorSiemens 350 kW, 2,986 rpm, safety factor 1.1

Condition found during overhaul

Measured data — surge test, clearances & alignment

Every overhaul we document with numbers, not only photos. Below is the measured data recorded in the overhaul report for this machine.

Surge test — before vs. after overhaul

Surge test pointBefore overhaulAfter overhaul
Surge point 10.901 MPa @ 44.5 A motor current0.801 MPa @ 45.1 A motor current
Surge point 21.257 MPa @ 63.7 A motor current1.034 MPa @ 64.4 A motor current

Both surge points were re-tested after the overhaul and the anti-surge set points were verified against the new data. The machine no longer surges inside its working range.

Rotor & stator clearances (IHI TRA clearance table)

Clearance positionMeasured
A — bull gear0.25 mm
B — high-speed shaft / low-speed shaft0.18 mm / 0.17 mm
C — impeller ↔ inlet scroll, 1st / 2nd / 3rd stage0.44 / 0.43 / 0.39 mm
D — diffuser shim thickness, 1st / 2nd / 3rd stage1.70 / 1.65 / 1.20 mm
E — shaft & bearing clearance, 1st / 2nd / 3rd stage0.15 / 0.14 / 0.16 mm
E — bull gear bearing, drive side / non-drive side0.15 / 0.16 mm

Coupling alignment (motor ↔ compressor, cold)

Control valve stroke test

ValveClose → openOpen → close
Inlet guide valve (IGV)18 s18 s
Blow-off valve23 s2 s

Photos from the job

The photos follow the order of the overhaul report, row by row. Each row covers one stage of the work, so a component stays in the same column from one row to the next — as found, after cleaning / grinding / testing, then after coating or replacement — which makes the change directly comparable.

Row 1 — intercooler cores and 3rd-stage scroll, as found

As foundIHI TRA350KW 1st stage intercooler core as found, relatively clean, light deposits only

1st-stage intercooler core — relatively clean

As foundIHI TRA350KW 2nd stage intercooler core as found with heavy rust on the cold side

2nd-stage intercooler core — heavy rust on the cold side

As foundIHI TRA350KW 3rd stage scroll casing and impeller as found with heavy rust in the flow path

3rd-stage scroll casing & impeller — heavy rust

Row 2 — intercooler cores after grinding; 2nd-stage impeller under PT

GroundIHI TRA350KW 1st stage intercooler core after grinding

1st-stage intercooler core — ground

GroundIHI TRA350KW 2nd stage intercooler core after grinding

2nd-stage intercooler core — ground

PT testIHI TRA350KW 2nd stage impeller with dye penetrant applied during test

2nd-stage impeller — dye penetrant applied

Row 3 — intercooler cores re-coated; 3rd-stage impeller PT result

CoatedIHI TRA350KW 1st stage intercooler core after protective coating

1st-stage intercooler core — coated

CoatedIHI TRA350KW 2nd stage intercooler core after protective coating

2nd-stage intercooler core — coated

PT resultIHI TRA350KW 3rd stage impeller after PT showing no crack indications

3rd-stage impeller — no cracks found

Row 4 — diffusers and 2nd-stage impeller, as found

As foundIHI TRA350KW 2nd stage diffuser as found, heavily rusted

2nd-stage diffuser — heavily rusted

As foundIHI TRA350KW 3rd stage diffuser as found, heavily rusted

3rd-stage diffuser — heavily rusted

As foundIHI TRA350KW 2nd stage impeller as found, surface wiped clean for inspection

2nd-stage impeller — wiped for inspection

Row 5 — diffusers after grinding

GroundIHI TRA350KW 2nd stage diffuser after grinding

2nd-stage diffuser — ground

GroundIHI TRA350KW 3rd stage diffuser after grinding

3rd-stage diffuser — ground

Row 6 — diffusers re-coated; 2nd-stage impeller PT result

CoatedIHI TRA350KW 2nd stage diffuser after protective coating

2nd-stage diffuser — coated

CoatedIHI TRA350KW 3rd stage diffuser after protective coating

3rd-stage diffuser — coated

PT resultIHI TRA350KW 2nd stage impeller after PT showing no crack indications

2nd-stage impeller — no cracks found

Row 7 — cooler end covers, as found

As foundIHI TRA350KW 1st stage intercooler front end cover as found with heavy scale

1st-stage front cover — heavy scale

As foundIHI TRA350KW 2nd stage intercooler front end cover as found with heavy scale

2nd-stage front cover — heavy scale

As foundIHI TRA350KW 1st stage intercooler rear end cover as found with heavy scale

1st-stage rear cover — heavy scale

Row 8 — cooler end covers, ground and re-coated

AfterIHI TRA350KW 1st stage intercooler front end cover ground and re-coated

1st-stage front cover — ground & coated

AfterIHI TRA350KW 2nd stage intercooler front end cover ground and re-coated

2nd-stage front cover — ground & coated

AfterIHI TRA350KW 1st stage intercooler rear end cover ground and re-coated

1st-stage rear cover — ground & coated

Row 9 — scroll casings, as found

As foundIHI TRA350KW 1st stage scroll casing as found with light rust

1st-stage scroll casing — light rust

As foundIHI TRA350KW 2nd stage scroll casing as found with light rust

2nd-stage scroll casing — light rust

Row 10 — scroll casings, re-coated

CoatedIHI TRA350KW 1st stage scroll casing after protective coating

1st-stage scroll casing — coated

CoatedIHI TRA350KW 2nd stage scroll casing after protective coating

2nd-stage scroll casing — coated

CoatedIHI TRA350KW 3rd stage scroll casing after protective coating

3rd-stage scroll casing — coated

Row 11 — stage inlet pipes and the new 1st-stage inlet scroll

CoatedIHI TRA350KW 2nd stage air inlet pipe after protective coating

2nd-stage inlet pipe — coated

CoatedIHI TRA350KW 3rd stage air inlet pipe after protective coating

3rd-stage inlet pipe — coated

New partIHI TRA350KW new 1st stage inlet scroll supplied for the overhaul

1st-stage inlet scroll — new part

Row 12 — new bearings, oil seals and air seals

NewIHI TRA350KW new low speed bearings for the 1st and 2nd stage

Low-speed bearings, 1st & 2nd stage — new

NewIHI TRA350KW new oil seals for the three stages and the bull gear

Oil seals, all stages & bull gear — new

NewIHI TRA350KW new air seals for the three stages

Air seals, all stages — new

Row 13 — bull gear parts, motor side

Motor sideIHI TRA350KW bull gear shaft and thrust face, motor side, in good condition

Bull gear shaft & thrust face — good condition

Motor sideIHI TRA350KW bull gear bearing thrust face, motor side, in good condition

Bearing thrust face — good condition

Motor sideIHI TRA350KW bull gear bearing, motor side, in good condition

Bull gear bearing — good condition

Row 14 — bull gear parts, main oil pump side

Pump sideIHI TRA350KW bull gear shaft and thrust face, main oil pump side, in good condition

Bull gear shaft & thrust face — good condition

Pump sideIHI TRA350KW bull gear bearing thrust face, main oil pump side, in good condition

Bearing thrust face — good condition

Pump sideIHI TRA350KW bull gear bearing, main oil pump side, in good condition

Bull gear bearing — good condition

Row 15 — check valves, as found

As foundIHI TRA350KW main oil pump check valve as found, worn

Main oil pump check valve — worn

As foundIHI TRA350KW auxiliary oil pump check valve as found, worn

Auxiliary oil pump check valve — worn

As foundIHI TRA350KW discharge check valve as found, valve plate damaged

Discharge check valve — damaged, unusable

Row 16 — check valves, replaced with new parts

NewIHI TRA350KW new main oil pump check valve

Main oil pump check valve — new

NewIHI TRA350KW new auxiliary oil pump check valve

Auxiliary oil pump check valve — new

NewIHI TRA350KW new discharge check valve

Discharge check valve — new

Full inspection record

The overhaul followed the IHI inspection checklist for the TRA series. Every item below was opened up and checked, and the work actually carried out on each part is listed here.

Item inspectedWork carried out
Air end & gearbox
Bull gear, tooth contact & meshing flankInspected, cleaned — good condition
High-speed / low-speed pinion gear & shaftInspected; light carbon on high-speed shaft cleaned
Bull gear shaft bearingInspected — good condition
High-speed pinion bearingsInspected — good condition
Low-speed pinion bearingsReplaced
1st / 2nd / 3rd stage impellers1st stage replaced; 2nd & 3rd cleaned & PT tested (no cracks)
1st / 2nd / 3rd stage scroll casingsCleaned, ground & re-coated
1st / 2nd / 3rd stage diffusersReplaced, with new diffuser shims
1st / 2nd / 3rd stage air inlet pipingCleaned & re-coated
1st-stage inlet scrollReplaced
1st / 2nd / 3rd stage air sealsReplaced
1st / 2nd / 3rd stage oil seals + bull gear oil sealReplaced
Coolers
No. 1 / No. 2 intercoolersCleaned; end covers ground & re-coated; new stainless gaskets
Oil coolerCleaned; scale removed
Drain traps & drain trap check valveInspected & cleaned
Lubrication system
Oil tank, heater & vacuum gaugeInspected & cleaned
Main / auxiliary oil pumpInspected; main oil pump coupling replaced, O-rings renewed
Oil filter, oil circuit check valvesReplaced
Controls, piping & other
Inlet guide valve & blow-off valveStroke tested & adjusted
Air filter element, oil filter elementReplaced
Main coupling alignmentRe-aligned, within ±0.15 mm
Protection devices & vibration probesFunction tested; gap voltage re-adjusted
Discharge check valveReplaced

Scope of work — parts replaced

In addition: grinding and protective re-coating of the intercoolers, scroll casings, diffusers and inlet pipes; dye penetrant inspection of the 2nd and 3rd stage impellers (no defects); cleaning of the oil cooler and intercooler copper tubes; coupling alignment within ±0.15 mm; vibration probe gap voltage re-adjustment; control valve stroke test; and a surge re-test after reassembly.

Post-overhaul operation record

The machine was restarted immediately after the overhaul. Discharge pressure, motor current, bearing temperatures and vibration all came back to normal, and the unit has run without surging since. All parameters were normal at restart.

Root cause & our recommendation

The rust and cavitation came from years of operation with moist intake air and a cooling-water side that was not treated: scale built up in the intercooler tubes and on the end covers, air-side dirt blocked the flow path, and the resulting higher inlet temperatures pushed the machine towards surge. For the next overhaul we recommend checking the impellers, diffusers, scroll casings and coolers, keeping the cooling water treated and the tube side cleaned, and holding the following spares: 1st-stage impeller, diffuser set, air and oil seals, low-speed bearings, intercooler gaskets, air filter and oil filter elements.

Planning an overhaul or need IHI TRA spare parts?

Turbomax supplies alternative spare parts and overhaul service kits for the IHI TRA and other IHI centrifugal compressor series — impellers, diffusers, inlet scrolls, scroll casings, air seals, oil seals, journal and thrust bearings, bull gear bearings, intercooler and aftercooler cores, air filters, oil filters and check valves — and supports overhaul projects worldwide. Our founder has 10 years of IHI field service experience.

Spare parts by model